Installation guide
SENSORRAIL IIIE ADRL3TRK SERIES  8200-0593-02, REV. A 
INSTALLATION GUIDE
5 of 34 
Installation Steps 
The following step numbers refer to pull-out 
drawings at the end of this document. 
CAUTION: Perform all
 steps carefully 
and methodically. DO NOT skip steps! 
1.  Install threaded rods 
2.  Install PVC holders 
3.  Install stirrups, eyebolts, and jointing plates 
4.  Install rail sections 
5.  Install anti-sway cables 
6. Insert copper tracks and 
trolley stop/retrieval tool 
7.  Install optical stop strips 
8.  Install PowerRail module 
9.  Install camera trolley (complete trolley 
stop/retrieval tool assembly) 
10.  Attach light reducing sections 
11. Clean rail 
12.  Check electrical connections 
13. Configure system 
14.  Install cowling 
15. Install end covers. 
Installation Requires a 
Laser Leveling Device 
A Hilti PR-15 rotating laser leveling device is used 
to level the rail during installation. Set the beam to 
intersect with a prominent horizontal feature on the 
rail. 
 WARNING! Wear protective eyewear 
when using a laser leveling device. Refer 
to the device manufacturer’s instructions 
for additional safety precautions. 
1. Install Threaded Rods 
Threaded rods secure the rail system to the ceiling. 
Each rod attaches to the ceiling using one of the 
following methods: 
-  Direct into the ceiling 
-  To red iron ceiling supports using a “fast grip” 
system such as a HILTI MF C31/8 
-  To a suspension bar such as a HILTI MQ-41 
between red iron when ceiling supports are 
spaced more then 2.5m (8.2ft) apart. 
The bottom of each rod attaches to a stirrup at the 
top of the rail section. 
Tools, Equipment, and Parts Required for 
this Operation 
•  Proper lift equipment (scissor lift with extended 
work platform is recommended) 
•  Hilti PR-15 rotating laser leveling device 
• String line 
•  M8 threaded rods (one per rail section) 
•  Saw (to cut rods) 
•  M8 nuts (one per rod). 
Procedure 
Note: Observe space requirements (page 3). 
A. Run a string line. 
•  Centered along the rail route 
•  10cm (4in) higher than the top of the rail. 
Tack the string in place. 
B. Install the first threaded rod. 
Each rod supports a rail section at its center. 
Install the first rod 1.25m (5.1ft) from where the 
first 2.5m rail section is to start. 
C. Install subsequent threaded rods. 
From the first rod, install subsequent rods every 
2.5m (8.2ft) along the string line to the point 
where the last rail section will be located. 
D. Thread nuts. 
On each rod, thread a nut up until its bottom 
touches the string line and 5cm (2in) of rod is 
below the nut. 
E.  Saw off any extra rod length beyond 5cm 
(2in). Do not use a cutter. 