Installation Instructions
Hydro Massage Products LLC • 303-341-1845 | FAX: 303-341-1850 • www.hydromassageproducts.com • service@hydromassageproducts.com
6
EXTENSION PANEL INSTALLATION (If Applicable)
Step 1. Slide front panel A onto front of tub.
Step 2. Slide top panel B over Tile Flange
Step 3. Refer to Detail A on fastening ange
to studs and sealing
If applicable,
The drain body
and hose muse be
installed horizontal
WALK-IN INSTALLATION PROCEDURES:
1. Bathtub must be set on a solid at surface, either concrete slab or a minimum 3/4" plywood sub-oor.
2. All adjustable feet must rmly contact with the oor.
3. The bath must be completely level from side to side and front to back on the top lip of the bath.
4. Plumbing hardware (faucet, hoses, and waste/overow) should be installed prior to setting tub in-place.
5. Filler panel is used for 60" opening installations. (if applicable)
6. The drain body is to be installed between the drain shoe and the drain tee. (if applicable)