Installation Guide

11
ADJUST SUPPLY STOP; Fig. 13
IMPORTANT: To avoid overowing, the SUPPLY STOP (3)
must never be opened to the point where the ow from
the valve exceeds the ow capacity of the xture.
Valve is designed to provide stated ush volume with a
25 gpm ow rate for toilet and 10 gpm ow rate for urinal.
1. Remove COVER (2) from SUPPLY STOP (3).Turn on
water supply 1/4 turn to 1/2 turn(CCW) and test for leaks.
Note: Unit may ush for approximately 5 to 10 sec. when
water is rst turned on.
2. Push down on HANDLE (4) to initiate ush.
3. Adjust SUPPLY STOP (3) after each ush until the
stated ush volume is achieved, no splashing occurs
and the xture is properly cleansed.
4. When adjustment is complete, reinstall COVER (2)
and tighten to ensure vandal-resistance.
12
HOW TO RETROFIT OUR VALVE; Fig. 14
(Replaces Industry Standard Manual and Electronic
Valves)
Note: In most Retrots the wall escutcheon, supply
stop, cover tube and vacuum breaker do not have to
be replaced. If these items do need replacement they
must be purchased separately or order the complete
ush valve assembly from American Standard.
1. Remove COVER (1) from SUPPLY STOP (2) if installed.
Fig. 14.
2. Turn water supply off. Fig. 14.
3. Unthread COUPLING NUT (3) and VACUUM BREAKER
COUPLING NUT (4). Remove FLUSH VALVE (5).Fig. 4a.
4. Clean all threaded connections before installing the new
ush valve. Fig. 14a.
5. Refer to Sections 4, 5 and 6 to complete the retrot
installation. Fig. 14b.
13
LEFT OR RIGHT HAND INSTALLATION;
Fig. 15
1. The FLUSH VALVE can be installed either as a right
or left hand installation.
2. Orientate the FLUSH VALVE as shown in Fig. 13 to
desired position for a left or right hand installation.
Fig. 13
2
REMOVE COVER
CLOCKWISE CLOSES
CONTROL STOP
COUNTER-CLOCKWISE
OPENS CONTROL STOP
3
2
Fig. 14 Fig. 14a Fig. 14b
1
5
3
4
CLEAN
CONNECTIONS
Fig. 15
Right or Left Hand Installation
Left Hand Right Hand
M965890 Rev. 1.1 (1/19)
7