PLUMB - LEVEL - SHIM
PLU
PLUMB - LE
2. Attach Head Jamb To Side Jambs
• Apply a 1/8" bead of Sealant (provided) to top end of
Side Jambs and position against Head Jamb.
Sealant must be applied to end of Side Jamb to
help prevent water infiltration.
Interior Edge
of Head Jamb
Side Jamb
Head Jamb
Interior
Edge
of Side
Jamb
#10 x 2-1/2" Stainless Steel Screws and Locations
When attaching Side Jambs to Head Jamb, screw
fastening sequence must be followed. Failure to do
so may result in incorrect fit of frame parts.
• Fasten Head Jamb to Side Jambs through predrilled holes
using four #10 x 2-1/2" Stainless Steel Flat Head Screws.
Screw fastening sequence must be followed.
Screw 1 : Fasten interior side of Side Jamb to Head Jamb.
Screw 2 : Fasten interior side of Head Jamb to Side Jamb.
Screw 3 : Fasten exterior side of Head Jamb to Side Jamb.
Screw 4 : Fasten center of Side Jamb to Head Jamb.
• Clean up excess squeeze-out of Sealant.
Sealant
Exterior Edge
of Head Jamb
1
2
3
4
3. Apply Side Installation Flanges
• Position Side Installation Flanges in groove on
frame, short leg pointing toward interior, flush
with bottom of Sill. Place wood block
against short leg of Side Installation
Flange and tap until fully seated.
Some masonry/concrete wall and replacement
situations do not require the use of Side Installation
Flanges. If Side Installation Flanges are not being
used proceed to Step 4.
Sill
Side Installation Flange
Side Jamb
Side Installation Flange
Flush with Bottom of Sill
Wood Block
• Position Head Jamb exterior side up
Exterior
Hammer
Exterior Side Up
Installation Flange
Short Leg
Exterior Side Up
BAG
A
Hardware
Needed
#10 x 2-1/2" Stainless Steel Screw
Frame Assembly and Installation Guide