APPENDIX A - VFD CENTRIFUGE HMI SERVER SYSTEM 
15 May 13  A-3 
Appendix A-HMIServerSystem 
Figure A-3. Electrical Connections to Router Switchgear Box 
3.  Tighten nut properly on cable gland to ensure proper sealing. 
4.  Close and secure cover of Router Switchgear Box after completing connections. 
5.  Plug in HMI Server and PC power cords. 
Ethernet Connections 
Required Equipment 
The following customer-supplied components are required for making the Ethernet connections: 
Item 
Purpose 
Quantity 
Category 5 (CAT5) or 
higher shielded 
Ethernet cable 
Connections between control 
cabinets, HMI Server, & Router 
Switchgear Box 
Maximum 328’ (100m) each 
1” NPT cable glands 
Ethernet cables from each 
control cabinet to routers in 
Router Switchgear Box 
1 for each centrifuge control 
cabinet 
Explosion-proof 3/4” 
NPT cable glands 
Ethernet & power cables into 
Router Switchgear Box 
Up to 7 for Router Switchgear Box: 
  1 for Power 
  2 or 1 for PC 
  1-4 for Centrifuges 
Ethernet switch/router 
Interconnect HMI Server and 
computer 
1 
PC or laptop computer 
Monitor up to 4 centrifuges 
1-3 (supports up to 3 connections) 
Server and PC Connection Requirements 
An Ethernet connection must be established between the Ethernet switches in the centrifuge 
control cabinets and the routers in the Router Switchgear Box. Ethernet connections are also 
required from the HMI server to the computer and Ethernet switch in the Router Switchgear Box. 