Specifications
  Document No.  DER01422 
  Effective Date  30 Aug 07 
  Page No.  1 of 3 
EQUIPMENT HANDLING PROCEDURES 
DE-7200 CENTRIFUGE 
RECEIVING THE EQUIPMENT 
Immediately upon receipt of the Derrick equipment, examine contents for damaged and/or 
missing components. The transportation company signed a bill of lading at the time of shipment to 
indicate that all items were present and accounted for, and all items were in good condition at the 
time of shipment. The transportation company assumes responsibility for the equipment from that 
point forward. For proper handling of your claim, immediately report any loss or damage to the 
transportation company. 
For material shortages not appearing on the bill of lading or for discrepancies between material 
ordered and material received, immediately notify Derrick Corporation. 
MOVING/POSITIONING THE EQUIPMENT 
WARNING! USE SPREADER BARS TO PREVENT DAMAGE WHEN LIFTING 
THE EQUIPMENT. 
WARNING! TO ENSURE PROPER BALANCE AND ORIENTATION WHEN UNIT 
IS RAISED AND PREVENT DAMAGE TO COMPONENTS, ATTACH LIFTING 
SLINGS ONLY TO LABELLED LIFTING POINTS. DO NOT ATTEMPT LIFTING 
BY ATTACHMENT TO ANY OTHER LOCATION. 
WARNING! BE SURE THAT HANDLING DEVICES HAVE SUFFICIENT LIFTING 
CAPACITY TO SAFELY HANDLE THE WEIGHT OF THE EQUIPMENT. 
WARNING! DO NOT REMOVE SHIPPING BRACKETS UNTIL EQUIPMENT HAS 
BEEN POSITIONED AT FINAL INSTALLATION SITE. 
WARNING! WHEN USING AN OVERHEAD LIFTING DEVICE, USE ALL FOUR 
LIFTING POINTS PROVIDED. 
The centrifuge is shipped fully assembled. The control cabinet is mounted on a shipping skid. A 
label indicating the weight of the unit was affixed to the machine. Refer to Equipment 
Specifications 
DER01222 for equipment weight and other technical data. 
The centrifuge may be transported on the ground using a forklift. After the control cabinet is 
removed from the shipping skid, an overhead lifting device is required. 










