EQUIPMENT HANDLING PROCEDURES
DE-7200 CENTRIFUGE
RECEIVING THE EQUIPMENT
Immediately upon receipt of the Derrick equipment, examine contents for damaged and/or
missing components. The transportation company signed a bill of lading at the time of shipment to
indicate that all items were present and accounted for, and all items were in good condition at the
time of shipment. The transportation company assumes responsibility for the equipment from that
point forward. For proper handling of your claim, immediately report any loss or damage to the
transportation company.
For material shortages not appearing on the bill of lading or for discrepancies between material
ordered and material received, immediately notify Derrick Corporation.
MOVING/POSITIONING THE EQUIPMENT
WARNING! USE SPREADER BARS TO PREVENT DAMAGE WHEN LIFTING
THE EQUIPMENT.
WARNING! TO ENSURE PROPER BALANCE AND ORIENTATION WHEN UNIT
IS RAISED AND PREVENT DAMAGE TO COMPONENTS, ATTACH LIFTING
SLINGS ONLY TO LABELLED LIFTING POINTS. DO NOT ATTEMPT LIFTING
BY ATTACHMENT TO ANY OTHER LOCATION.
WARNING! BE SURE THAT HANDLING DEVICES HAVE SUFFICIENT LIFTING
CAPACITY TO SAFELY HANDLE THE WEIGHT OF THE EQUIPMENT.
WARNING! DO NOT REMOVE SHIPPING BRACKETS UNTIL EQUIPMENT HAS
BEEN POSITIONED AT FINAL INSTALLATION SITE.
WARNING! WHEN USING AN OVERHEAD LIFTING DEVICE, USE ALL FOUR
LIFTING POINTS PROVIDED.
The centrifuge is shipped fully assembled. The control cabinet is mounted on a shipping skid. A
label indicating the weight of the unit was affixed to the machine. Refer to Equipment
Specifications
DER01222 for equipment weight and other technical data.
The centrifuge may be transported on the ground using a forklift. After the control cabinet is
removed from the shipping skid, an overhead lifting device is required.