LIQUID AND SOLID DISCHARGE CHUTES 
Observe the following design considerations when fabricating the liquid and solid discharge 
chutes. To determine dimensions and mounting hole arrangements, refer to drawing 16590-00 in 
Section 11. 
Liquid Discharge Chute 
When fabricating the chute, be certain to make the chute as straight as possible. Minimal curves 
are acceptable, but that will restrict flow away from the centrifuge should be eliminated from the 
chute design. 
Solid Discharge Chute 
The solid end chute should be designed at a sufficiently steep angle to facilitate self cleaning. If 
this is not possible, a means should be included to periodically remove accumulated solids from 
the chute. 
EQUIPMENT LEVELING 
The centrifuge must be properly leveled for satisfactory operation. The equipment must be leveled 
along the length and width of the unit (Figure 3022-3). A 2-foot or torpedo level is recommended. 
Non-compressible shims should be used as required to level the machine. 
Figure 3022-3 Centrifuge Leveling 