INITIAL STARTUP 
Perform the initial startup procedure when the centrifuge is being started for the first time following 
installation or after the machine has been relocated. Before beginning the procedure, verify the 
following: 
1.  All tools, documents, and shipping components have been removed and there are no 
obstructions to operation. 
2.  All personnel are clear of equipment. 
INITIAL STARTUP 
Step   Procedure 
1 
Confirm that all operators and maintenance personnel have read and understand all 
operating and safety information in Section 2 - Safety. 
2  Check that services and utilities are available at the installation site per DER01321. 
3 
Verify that equipment has been installed properly, all shipping brackets have been 
removed, and bearing pillow blocks have been tightened to specified torque per 
DER03022. 
4 
Apply power to centrifuge, and run bowl at 20 RPM with a conveyor differential speed of 
5 RPM. Confirm direction of rotation for bowl, conveyor, feed pump, and air conditioner 
condenser motors as follows: 
• Bowl - Counterclockwise viewed from fan end 
• Conveyor - Clockwise viewed from fan end 
• Feed pump - Per manufacturer’s data 
• Air conditioner condenser - Clockwise viewed from fan end 
Correct reverse rotation by shutting down power and switching any two of the three 
power leads at the terminal block(s) inside the cabinet (refer to 
DER03022 and electrical 
schematic diagram in Section 11. 
5 
With electric power applied, but without centrifuge running, perform the following safety 
checks: 
• Operate emergency stop buttons on junction box and control cabinet, and confirm 
that Emergency Stop alarm message appears on control panel. 
• Tap vibration switch housing horizontally with a rubber or rawhide mallet, and 
confirm that High Vibration Fault message appears on control panel. 
These tests confirm that connections have been correctly made between control cabinet 
and centrifuge. 
6  Start centrifuge in accordance with Normal Startup procedure below. 