3 4
8” Box Out
5
Mark fitting locations. (Refer to measurements from step 3.) Using a hole saw (fine
tooth or abrasive grit cutting edge), make necessary openings for filler and valves,
drilling from inside (smooth side) out.
If mounting fittings — from stable reference points (back wall studs, floor)
measure the locations of spout and valves. Note measurements.
INSTALLATION PROCEDURE, CONT.
Check for level. Check for proper floor slope (1/4” per foot) by placing level in
locations shown above and measuring slope along the length of the level.
6
7 8
Fasten vertical nailing flanges to studs starting from the floor, moving upward
every 8 inches. Fasten horizontal nailing flanges at every stud.
Cover the entire bottom of the unit with a piece of cardboard or other protective
material. Pre-drill pilot hole and fasten the center of the back nailing flange to
stud to secure unit in place. Once secured proceed by pre-drilling pilot holes
and fastening unit to floor starting in the center of the base flange, moving
outward every 8 inches.
Place the unit directly on level floor (or on top of foundation materials) with drain
fitting over and onto waste pipe with threshold firmly on the floor. A
ssure waste
pipe protrudes well into drain fitting. Maintain proper floor slope towards drain.
Level Placement