6.3.2 - VERIFICATIONS
Purging of circuits.
Hydraulic pressure (1.5 to 2.5 bar).
Water flowrate: the unit is equipped with 1/4 SAE pressure taps at the circulator inlet and outlet (see paragraph 2.1.1),
so that the pressure loss can be measured using a hydraulic pressure gauge. Use the circulator curves below to
determine the water flow rate.
In order for the apparatus to work properly, the nominal flow rate must be respected.
6.3.3 - CIRCULATOR CURVES
HKBE - HKCE - HKDE
Circulator UPML 32-95-180 AUTO
6.3 - ADDITIONAL HYDRAULIC CIRCUIT VERIFICATIONS
6.3.1 - FORCED CIRCULATOR OPERATION
In order to conduct the final verifications of the hydraulic circuit, force the pump to start as follows (installation power
ON):
- Set the system control unit to “OFF”.
- Temporary turn off the circuit breaker Q4.
- Set microswitch SW3 of the control PCB A2
in
configuration “Terminal unit or mixed zone”
OFF-OFF.
- Turn on the circuit breaker Q4.
- Press and hold the button for 5 seconds.
The circulator starts.
The circulator indicator light flashes.
- Check that the “H
2
O” flow indicator is illuminated.
NOTE: Don’t make the outdoor unit operate during the setting of microswitch SW3.
Q4
NU
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0
Q [m³/h]
0
2
4
6
8
10
[m]
H
0
20
40
60
80
100
[kPa]
p
CP
PP
CP3
CP2
PP1
PP2
PP
3
CP1
2.1 HKDE + O.U . SIZE 140
1.9 HKBE/HKCE + O.U . SIZE 140
1.9 HKBE/HKCE/HKDE + O.U . SIZE 110
1.65 HKBE/HKCE + O.U. SIZE 80
1.4 HKBE + O.U. SIZE 65
0.9 HKBE + O.U. SIZE 50