Installation Guide

A
RMOR DOO
R
TM
INSTALLATION OF WELDED FRAMES
2. STEEL STUD WALLS
Installation
of a hollow metal frame in steel stud
wall, Figure 11.
Refer to HMMA 820 Hollow Metal
Frames for additional anchorage methods.
FIGURE 13
DRYWALL STUD ANCHOR
INSTALLATION ON FRAME
SPREADERS
90
?
JAMB
STUDS
CEILING RUNNER
HEADER STUD
FLOOD RUNNER
90
?
Combination wood / steel stud anchors, Figure 12
& 13
, are welded (optional) or friction fit inside the
jamb. Additional horizontal straps allows fastening
to the face of the stud in lieu of through the throat.
Typically used when the steel stud wall is
assembled prior to setting the frame.
Position the vertical steel studs in the frame throat
opening in accordance with architect’s details.
Attach the vertical steel studs to floor and ceiling
runners and fasten to the steel stud anchors with
mechanical fasteners.
FIGURE 12
DR
YWALL STUD ANCHOR
FIGURE
11
STEEL STUD
WALL