Installation Guide

Open cartons 2-3 days prior to the install and allow material to adjust to the relative humidity
in the space where it will be installed. Maintain consistent humidity levels after installation.
For the best fi nished appearance, mix planks from multiple cartons while installing.
Ensure proper gaps are maintained around the perimeter of the room and all obstructions.
Ensure the surface is level and planks are able to slide freely within their clips.
This is a fl oating ceiling and planks should not be attached directly to trim, molding or walls
in a ceiling application.
Never span more than 21-ft without an expansion joint (cover with trim).
5-in x 84-in x 3/8-in
12.7 cm x 213.36 cm x 9.525 mm
10 planks | 29 sq.ft.