Instructions / Assembly
20
20AP
You will need for this page:
(QTY: 18+)
(QTY: 6+)
Assemblies from Step 1:
•  All remaining Truss 
 Assemblies
10632
Side Frame
2+
10887
Side Wall 
Channel
2+
6
57 1/2” (146,1 cm) behind the previous Truss, 
erect a Truss Assembly and secure using a Large 
Screw on each side. Once two Truss Assemblies 
are in place, connect them with a Mid Side Wall Channel 
and secure with Large Screws. Support Trusses until Mid 
Side Wall Channels are in place.
LS SB
5
All  Truss Sections are assembled in the 
same manner as the Truss Section just 
erected. Install one additional Side Frame 
per side for each additional Module. Overlap Side 
Frames by 8 1/4” (21,0 cm). Refer to page 13 to 
see how many Trusses should be included in your 
building.
One Side Frame per side is added for
each additional Extension Module.
10650
10650
10650
10887
10887
10632
10632
Install the Main Roof Beam and secure with two 
Small Bolts and Nuts at each end. Next, install 
the outer Roof Beams in the same manner.
8
Remove Bolts holding Truss peaks together (from 
Step 1-6). Next, place two Middle Roof Beams 
back-to-back and secure with two Small Bolts 
and Nuts as shown. This is the Main Roof Beam.
7
If you are erecting a 10’x10’ (3,0 m x 3,1 m) building, skip this page 
and move on to page 21.
10650
10650
Main Roof Beam
Side of Beams with small holes must face up.
Outer
Outer
Outer
Main
Outer
Main
Repeat until all Trusses have been installed.
Roof Beam
4+
10650
Step 4: 
Continued for Extension Modules