Parallel Solvent Addition and Vessel Draining 
on the solvent line and a Teflon bottle seal is present in the cap. Wait a minute or so 
for the bottle to pressurize. 
2. 
Toggle the "Upper Manifold Membrane" switch to "Open." 
3. 
Initialize the solvent flow to the reaction vessels by setting the left Manifold Control 
Valve to Solvent, and the right valve to Vent: 
drain 
solvent  closed 
utility 
1 
metered gas 
vent 
0 
closed 
utility 
2 
4.  When the reaction vessels have been filled to the desired level, rotate the left hand 
Manifold Control Valve from solvent to drain, as this will blow residual solvent 
from the Upper Manifold common path into the vessels (about 
1 
sec is required): 
drain  metered gas 
solvent  closed 
utility 
1 
vent 
0 
closed 
utility 
2 
5. 
After blowing the residual solvent into the vessels, set both Manifold Control 
Valves to "Closed": 