Specifications

Parallel Solvent Addition and Vessel Draining
on the solvent line and a Teflon bottle seal is present in the cap. Wait a minute or so
for the bottle to pressurize.
2.
Toggle the "Upper Manifold Membrane" switch to "Open."
3.
Initialize the solvent flow to the reaction vessels by setting the left Manifold Control
Valve to Solvent, and the right valve to Vent:
drain
solvent closed
utility
1
metered gas
vent
0
closed
utility
2
4. When the reaction vessels have been filled to the desired level, rotate the left hand
Manifold Control Valve from solvent to drain, as this will blow residual solvent
from the Upper Manifold common path into the vessels (about
1
sec is required):
drain metered gas
solvent closed
utility
1
vent
0
closed
utility
2
5.
After blowing the residual solvent into the vessels, set both Manifold Control
Valves to "Closed":
QUEST
210
User
Manual
Artisan Technology Group - Quality Instrumentation ... Guaranteed | (888) 88-SOURCE | www.artisantg.com