Specifications

Argonaut Technologies
The following information provides space, electrical, gas, waste, and ventilation requirements for the
Automated Solvent Wash Option. Adherence to the following will result in trouble free installation.
5.1
Space
Requirements
The space requirements for the ASW Controller Unit remain the same as the standard Quest and can
be found in the Quest User Manual. The
ASWM
requires bench space that is
17
inches wide,22
inches deep and
18
inches tall within a fume hood. This bench space must be capable of supporting
58
pounds and be located between the Reactor and Controller units. See Figure
1
for the recommended
set-up of a Quest
210
with the Automated Solvent Wash Option.
*tor
Unit
,Automated Solvent Wash Module
,ASW
Controller Unit
Figure
1
-Recommended Set-up of a Quest
210
with the Automated Solvent Wash Option
Note: The ASW Controller Unit must be placed external to the fume hood. Sensitive electronic
assemblies could be degraded and/or damaged if placed in an environment with a high level of
chemical vapors.
5.2
Electrical Requirements
The electrical requirements for the ASW Controller Unit are the same as for the standard Quest and
can be found in the Quest manual. Since the ASWM is controlled pneumatically there are no
additional electrical requirements.
Artisan Technology Group - Quality Instrumentation ... Guaranteed | (888) 88-SOURCE | www.artisantg.com