Specifications
Argonaut  Technologies 
The following information provides space, electrical, gas, waste, and ventilation requirements for the 
Automated Solvent Wash Option. Adherence to the following will result in trouble free installation. 
5.1 
Space 
Requirements 
The space requirements for the ASW Controller Unit remain the same as the standard Quest and can 
be found in the Quest User Manual. The 
ASWM 
requires bench space that is 
17 
inches wide,22 
inches deep and 
18 
inches tall within a fume hood. This bench space must be capable of supporting 
58 
pounds and be located between the Reactor and Controller units.  See Figure 
1 
for the recommended 
set-up of a Quest 
210 
with the Automated Solvent Wash Option. 
*tor 
Unit 
,Automated Solvent Wash Module 
,ASW 
Controller Unit 
Figure 
1 
-Recommended  Set-up of a Quest 
210 
with the Automated Solvent Wash Option 
Note: The ASW Controller Unit must be placed external to the fume hood. Sensitive electronic 
assemblies could be degraded and/or damaged if placed in an environment with a high level of 
chemical vapors. 
5.2 
Electrical Requirements 
The electrical requirements for the ASW Controller Unit are the same as for the standard Quest and 
can be found in the Quest manual.  Since the ASWM is controlled pneumatically there are no 
additional electrical requirements. 