Installation Guide
Fig. 16
Fig. 17
Step 4b: No Nail Fin Door Installation
A) Remove all packaging material (blocks, pads, protectors, stretch wrap)
B) Inspect and verify the following:
a. The door unit is the correct size and configuration.
b. The unit is free from any damage or defects.
C) Contact your nearest Ashworth distributor if there are any problems with step B above.
D) Measure in from the exterior side of the unit 2 5/8" and mark this at four equally spaced
points along each side jamb and three equally spaced points along the head jamb. Then drill a
1/8" pilot hole through the entire unit at each of the 11 marked places. (Fig. 16)
E) After the pilot hole has been created, drill a 25/64" hole through the aluminum cladding only.
(Fig. 16)
F) Test fit the unit in the rough opening and set the unit to the appropriate jamb depth. Once the
correct jamb depth has been determined, draw a line along the inside of the sill on the
subfloor. (Fig. 17)
G) Remove the unit from the opening.