Specifications
AT 52
would recharge the battery after just two hours, 
while a cheaper 62.5W panel would require 
eight hours.
Solar panels are available in many different sizes 
and power ratings. Sometimes it is not possible 
to get a single solar panel with sufficient output 
power. In this case, two or more solar panels can 
be connected together in parallel. The example 
above required a solar panel rated at 125W. 
A single 125W solar panel would do the job 
nicely, but other combinations are possible. Two 
60W solar panels wired in parallel will produce 
120W. Likewise, four 30W solar panels wired in 
parallel will also produce 120W. (Both of these 
examples represent a shortfall of 5W per hour, 
or a total of 20W during the four-hour peak 
sunlight recharging period. This is acceptable 
because the panels will almost certainly be 
exposed to more than four hours of sunlight per 
day, allowing them to make up the difference 
– a 120W panel will produce the extra 20W in 
10 minutes of additional peak sunlight.)
The ability to combine solar panels has another 
benefit if the budget is tight. For the example 
above, it may be possible to start with a single 
60W solar panel and add a second solar panel 
when the budget permits. The downside is 
that a 60W solar panel will take longer to 
recharge the battery. If, however, you lived in 
an area that got considerably more than four 
hours of peak sunlight per day, a 60W solar 
panel might be sufficient. Likewise, if the 
audio technology was only used on alternating 
days (e.g. Monday, Wednesday, Friday, etc.), a 
60W solar panel would have plenty of time to 
recharge the battery. If the audio technology was 
only used one day per week (e.g. Saturdays), an 
inexpensive 30W solar panel would have plenty 
of time to recharge the system during the week.
One final note: The effectiveness of a solar 
panel is affected by its physical positioning in 
relation to the movement of the sun across the 
sky. Careful positioning is required to maximise 
the output power. This is where the voltage 
and current indicators provided on the more 
expensive charge controller/regulators come in 
handy – by monitoring the output voltage of 
the solar panels, it’s possible to fine-tune their 
position for optimum output power.
Now that we know the battery and solar panel 
requirements, we must consider the devices 
that interface them together and to the audio 
technology they are powering: the charge 
controller, the regulator, the inverter and the 
UPS power board.
The charge controller must be able to withstand 
the highest current the solar panel is capable of 
producing, which is known as its ‘short circuit 
current’. Incorporating a safety factor of 1.5 
ensures the charge controller is never pushed to 
its maximum capability. So, if the solar panel’s 
short circuit current is 5A, a charge controller/
regulator rated at 5 x 1.5 = 7.5A would be a 
good choice. (Note that if you are using two or 
more solar panels in parallel, you must add the 
short circuit currents together to arrive at a total, 
which the safety factor is then applied to.)
The regulator must be able to pass current 
from the battery to the inverter without being 
damaged from overheating. The system used in 
the example above drew a total of 12.5A from 
the battery – the regulator must be capable of 
passing this current. Again, a safety factor of 1.5 
is worth considering, suggesting a minimum 
of 18.75A, which we’ll round up to 20A to suit 
commercially available products. Likewise, the 
inverter must be able to accept this current from 
the regulator and deliver 136W of AC power to 
the audio technology – a 150W inverter would 
be the minimum choice for this purpose, but a 
200W inverter would be wiser.
The wiring used to interconnect all the 
components must also be considered. Solar 
power systems are low voltage systems, and 
that means they need much higher currents 
to produce power. The 12V system described 
here needs 12.5A of current to produce 150W 
of power. In comparison, a 240V AC system 
needs only 0.416A to produce the same power. 
Passing 12.5A of direct current (DC) through a 
wire safely and efficiently requires heavy-duty 
wiring – even the power leads used for domestic 
appliances are insufficient for this application. 
This is why the wiring used for car batteries 
is so thick; a larger diameter wire has less 
resistance, and is therefore capable of passing 
a higher current with greater efficiency and 
safety. If the wire is too thin and has too much 
resistance, it will create a voltage drop (resulting 
in a loss of power) and may even overheat and 
cause an electrical fire. The companies that 
provide solar power equipment can recommend 
suitable wiring.
The UPS power board must provide sufficient 
back-up power to keep the audio technology 
running for about 10 minutes; more than long 
enough to save your work and either shutdown 
or change over to mains power. For the example 
given here, the UPS should be able to provide 
136W of power for 10 minutes. Most UPS 
power boards come with a chart showing how 
long they can power different systems.
The audio technology used for this example is 
typical of the smaller systems used in project 
studios. Based on the calculations above, the 
minimum requirements to power this system 
are:
1 x 125W solar panel
1 x 47A/h deep cycle battery 
1 x 20A charge controller/regulator 
1 x 150W inverter
1 x UPS power board
Taking advantage of on-line purchasing 
discounts from local suppliers, a suitable system 
can be purchased for approximately $2000.
This cost may seem high, but remember that 
the calculations used very conservative figures, 
erring on the side of caution, to propose a solar 
power system that should reliably provide three 
hours of power per day, every day – along with 
UPS back-up for easy transfer to mains power 
“ 
”
As calculated in the 
example, a 12V battery 
must provide 12.5A 
to the inverter. That’s 
a significantly high 
current and will require 
heavy-duty wiring between 
the battery, charge 
controller/regulator and 
the inverter. If a 24V 
battery and inverter were 
chosen, this current would 
halve. Here’s the maths: 
to produce 150W from 
a 24V battery requires 
a current of 150 / 24 = 
6.25A. So, a 24V battery 
that can supply 6.25A for 
one hour will be able to 
provide 150W for one hour. 
Because the system will 
be used for three hours 
per day, every day, the 
total A/h requirement for 
a 24V battery is 6.25 x 
3 = 18.75A/h. Factoring 
in a maximum discharge 
depth of 80% means the 
total A/h requirement of 
the 24V battery would 
be 18.75 / 0.8 = 23.4A/h, 
which we’ll round up to 
25A/h.
For smaller systems, like 
the one in this example, 
12V technology is usually 
the most cost-effective. 
With larger systems, 24V 
technology may prove to 
be more cost-effective.






