User Manual

ADCP-XX-XXX • November 2000 • Section 5: WMTS Operation
Page 5-3
2000, ADC Telecommunications, Inc.
Switched
Hub
NMS
Station
and
Servers
WMTS
VHF
Upconverter
Attenuator
Diplexer
Attenuator
WMU
CPE
Converter
Figure 5-1. Basic Test Setup
2.2.2 Test Procedure
Following the installation of the NMS and IP Servers, the test setup has to be completed and
the WMTS and WMU configured. The switched hub has to be configured to 100BaseT.
During configuration, all the system components have to be operational.
Observe the LED indicators to verify that all system components are operating properly.
Following the configuration of the various devices and invoking the servers, initiate a Ping test
from the NMS station toward the CPE connected to the WMU and vice versa. During the Ping
test, messages are exchanged between the CPE and the NMS station. While the Ping test is
being performed, the system must be operational. If the Ping test is passed successfully, the
system can be extended to integrate the wireless devices and proceed to the extended test.
2.3 Extended Test
2.3.1 Test Setup
The extended test is executed only after the basic test is successfully completed.
The extended test is an end-to-end test and includes the wireless components of the system as
illustrated in Figure 5-2. The wireless components may change according to the final setup of
the RF front-end of the system.