User's Manual

ORION® SE Network Gateway Transceiver
Using the V-block Clamps
This mounting equipment is sized to mount the network gateway transceiver on a vertical or horizontal pole with outer
diameters ranging from 1-1/4 inches to 2-1/2 inches. For mounting on poles larger than 2-1/2 inches, refer to "Banding
Mounting" on page 9.
1. Open the bag of mounting equipment.
2. Place two bolts (3/8-16 x 5 inches) through the holes in the top of the network gateway transceiver mounting
backplate (Figure 3). Use the side holes for horizontal installation.
3. Place a clamp onto the bolts, as shown below.
4. Place a lock washer and nut onto each bolt, as shown below.
NOT:N The lock washer and nut nearest the enclosure mounting bracket may be omitted when mounting on smaller
diameter poles to provide additional clamping distance.
Figure 3: Attach Hardware
5. Tighten the two nuts with a 9/16-inch or adjustable wrench so that each lock washer is fully compressed and at.
6. Repeat Steps 2 through 5, attaching a clamp to the bottom of the network gateway transceiver mounting backplate.
Position the network gateway transceiver on the pole and place a clamp on the top bolts.
Figure 4: Transceiver Positioning and Clamps
Bolts
Clamps
Nuts
Lock
Washers
Lock
Washer
Page 8 June 2012