User's Manual

Installation Data
6. Using the required Gel Splice Crimping Tool (59983-001), place the connector with the wires into the jaws of the
crimping tool.
Figure 19: Connector in Crimping Tool
Crimp the connector by squeezing the handles until the connector is completely compressed. The crimp tool is
designed to prevent applying too much pressure to the gel cap. Continue to apply pressure for three seconds.
Figure 20: Compress Connector
7. Attach the two plastic cable ties and tighten securely for strain relief. Snip o the excess cable tie with the wire cutter.
For remote installations, the connection is complete.
Figure 21: Wire Tie Attachment Locations
NOTE: For pit installations, it is advisable to test the connections before completing step 8.
8. For pit installations, place all three connected wires with gel caps into the eld splice tube provided in the
installation kit. Make sure the wires with gel caps are inserted as far as possible into the eld splice tube. Close the
eld splice tube. The connection is now complete.
Testing the Wire Connections
The connection of the encoder and ORION Universal endpoint can be tested using an ORION data collector. It is
recommended that all wiring connections be tested while on site. To test, set the data collector into the Quick Read function.
Encoder Register Installation
Install an RTR or ADE on the water meter and secure it using either the TORX screw or standard seal screw provided.
RTR Endpoint
Once the Pit ORION endpoint is securely installed and the RTR is mounted on the water meter, the ORION system is ready for
operation. Run water through the meter to increment the RTR 1/10th of the test circle. Upon receiving the rst digital signal
from the RTR, the endpoint counts the signal and begins its radio frequency transmissions. No specic testing of the wiring or
programming of the endpoint is required. Reading each pit endpoint immediately after installation veries proper
operation and reading performance. ORION reading equipment only can be used to read installed ORION endpoints.
Snipped Wire Ties
Gel Cap Connectors
11-11