Manual
SERVICING PARTS AND ASSEMBLIES
When the performance of a Turbo meter indicates a need for 
servicing, refer to the following instructions pertaining to removal, 
inspection and installation of service parts and assemblies. Also 
see the Recordall Turbo Series Meter Parts List for part numbers 
of replaceable components and correct ordering information. If 
satisfactory repair cannot be made, contact Badger Meter. 
Removing the Meter Head
Recordall Turbo Series meters can be serviced without removing 
them from the line. A typical installation would be equipped with 
drain and piping valves. To inspect or replace components of 
the head assembly, close the upstream and downstream valves. 
However, if the installation does not have a drain valve, proceed 
as follows to relieve pressure:
UPSTREAM AND DOWNSTREAM VALVES MUST BE CLOSED 
BEFORE ATTEMPTING TO REMOVE METER HEAD FROM 
HOUSING. FAILURE TO DO SO CAN LEAD TO THE HEAD BEING 
"EJECTED" FROM HOUSING, CAUSING PERSONAL INJURY 
AND/OR PROPERTY DAMAGE!
1.  Loosen each of the head bolts about 1-1/2 turns. Do not 
completely remove the bolts.
2.  If the O-ring between the meter head and the housing 
is secure and not leaking, pry the measuring element 
assembly loose by inserting a screwdriver blade where the 
head and housing join together.
BE SURE THAT ANY WATER COMING OUT OF THE METER HEAD 
DOES NOT SPRAY ONTO ELECTRICAL EQUIPMENT AND CREATE 
A SHOCK HAZARD.
3.  Allow the meter to drain and relieve internal pressure.
4.  When pressure is relieved, remove the head bolts. Lift the 
measuring element assembly from the housing.
Removing the Local Register or Encoder
The Recordall Turbo Series meter registers and encoders are easily 
removable to facilitate in-line service. 
1.  Remove the register lid and shroud by removing the seal 
screw. 
2.  Remove the shroud by rotating the register assembly 
counterclockwise until it stops. This provides clearance so 
it can be lifted o the measuring element assembly. See 
Figure 3 and Figure 4.
To reinstall the register, follow the above procedure in 
reverse order.
Figure 3: Removing the meter head assembly, 1-1/2" to 4" meters
Figure 4: Removing the meter head assembly, 6" meters
Recordall® Turbo Series Meters
Page 12  April 2014