Owner's manual
Installing the Meter
1.  Install the meter in the pipeline making sure that the ow arrow on the meter housing is in proper relation to the 
direction of liquid ow. It is also recommended that ten pipe diameters upstream and ve pipe diameters downstream of 
straight pipe be incorporated with no obstructions. If this is not possible, please contact factory to review acceptability 
of installation.
2.  Install and tighten the ange connection bolts.
3.  To relieve possible strain on the piping due to the weight of 4" and 6" turbo meters, it is recommended that consideration 
be given to installation of a meter support under the meter housing.
U
Figure 1: Recommended Meter Installation
Performance Checks
Complete the following checks to ensure that the meter is properly installed and operational.
1.  Slowly open the upstream valve to apply liquid pressure to the meter and check the ange connections for possible leaks. 
Retighten the ange bolts as required.
2.  Perform a functional test of the turbo meter using the adjustment and calibration procedure in this manual.
Bypass 
(Permanent 
or 
Temporary)
Upstream
Valve (open)
Minimum of 5 
diameters of 
straight pipe
Minimum of 2 
pipe diameters 
downstream of 
Turbo meter
Test tee
Downstream
Shutoff 
valve
Service 
saddle
Coupling 
adapter
Badger Meter plate 
strainer and Turbo meter
Industrial Turbo Meters, Sizes 2" through 6"
Page 6  November 2013