User Guide
Table Of Contents
- Application
- Features
- Applicable Literature
- SPECIFICATIONS
- VALVE SIZING AND SELECTION
- Water
- Cavitation Limitations on Valve Pressure Drop
- Additional Valve Sizing Information
- INSTALLATION
- Inspection
- Requirements
- Mounting
- 1. The valve should be mounted in a weather-protected area in a location that is within the ambient limits of the actuator. When...
- 1. Apply pipe dope sparingly to all but the last two threads of a properly threaded, reamed, and cleaned pipe. Make sure that pi...
- Table-6 Normal Thread Engagement Between Male Pipe Thread and Valve Body.
- Figure-3 Normal Thread Engagement.
- Figure-4 Installation of Screwed End Valves.
- 1. All parts should be clean to assure the best results.
- 2. The pipe with the companion flanges installed should be properly supported and aligned. Be sure the companion flange is flush with the face of the valve body flange and lined up squarely.
- 3. Use a gasket material (not provided) that is recommended for the medium being handled.
- 4. See Figure-5 for flange and flange bolt details. Figure-5 also shows the proper way a flanged valve should be mounted.
- Figure-5 Installation of Flanged End Valves.
- TYPICAL PIPING
- CHECKOUT
- 1. Make sure the valve stem operates freely before installing the valve linkage and the actuator.
- 2. If the stem does not operate freely, it may indicate that the valve was twisted or crushed during installation or that the stem was bent by rough handling. These conditions may require that the valve be replaced.
- 3. After the piping is under pressure, check the valve body and the connections for leaks.
- 4. After the valve linkage and the actuator are installed, check their operation.
- a. Drive the actuator and run the valve to the stem down position. Make sure the linkage and valve stem move freely. At the stem down position, the valve should shut off the “B” port.
- b. Drive the actuator and valve to the stem up position. Again, the valve stem and linkage should operate smoothly. At the stem up position, the valve should shut off the “A” port.
- 1. Make sure the valve stem operates freely before installing the valve linkage and the actuator.
- MAINTENANCE
- Water System Maintenance
- DIMENSIONAL DATA
Printed in U.S.A. 1/10 © Copyright 2010 Schneider Electric All Rights Reserved. F-24393-3
Application
VB-9313 series three-way mixing valves control hot or
chilled water in heating or air conditioning systems.
These valves must be piped with two inlets (“A” and “B”
ports) and one outlet (“AB” port). They are used for two-
position or proportional control applications. Valve
assemblies require an actuator and a valve linkage that
must be purchased separately.
Danger: Do not use for combustible gas applications.
The VB-9313 series valve packings are not rated for
combustible gas applications, and if used in these
applications, gas leaks and explosions will result.
Features
• Valve sizes 2-1/2" to 6".
• 250 psig pressure rating per ANSI Standards
(B16.15–1985) for screwed cast bronze bodies.
• 125 psig pressure rating per ANSI Standards
(B16.1–1993) for flanged cast iron bodies.
• Spring-loaded TFE packing.
Applicable Literature
• Valve Products Catalog, F-27384
• Cross-Reference Guide, F-23638
• Reference Manual, F-21683
• Application Manual, F-21335
• Valve Selection Guide, F-26094
• Control Valve Sizing, F-13755
• Valve Selection Chart for Water, F-11080
• EN-205 Water System Guidelines, F-26080
VB-9313 Series
2-1/2" and 3" Screwed NPT
2-1/2" to 6" 125 Lb. Flanged
Three-Way Mixing Valves
General Instructions
Typical of VB-9313-0-5-P
2-1/2" to 6"
Typical of VB-9313-0-4-P
2-1/2" and 3"