Instructions / Assembly

Secure the trusses to the sidewall that
has the wall bracing first. Make sure
the opposite sidewall is straight before
securing trusses. The building width
should be 12'-0" measuring outside of
2x4 tie plate to outside of 2x4 tie plate.
IMPORTANT
Step 20 Install Loft Flooring
1. Install (4) four trusses with the wood gusset on
the line and the truss bottom over the 'X' marks.
2. Secure trusses with the metal hangers
and 1-1/2" long hanger nails.
Step 19 Set Trusses
1. Install (2) two 4x8 sheets of loft flooring on trusses.
Notch floor around studs in the rear gable.
2. If necessary, cut flooring to the center of the 2x4.
3. Install the remaining trusses and the front gable panel
4. Install 4x8 sheets of loft flooring on trusses at the front of the building.
Make sure the walls are straight
before nailing flooring. Nail
floor to bottom 2x4 of gable and
trusses with 7d coated nails.