Once all of the copper lines are connected, vacuumed down to 500
microns, and the refrigerant is released, start the system.
Ensure the gauges do not show any restriction
Remove gauges once the system is operating properly.
NOTE
It is harmful to remove the gauges while the lineset is under vacu-
um. Keep the gauges connected until the vacuum is complete and
the refrigerant has been released into the lineset.
Multizone:
Connect each zone’s copper lines one at a time. After connecting the first
set of copper lines, and the pressure test is complete, connect your mani-
fold gauges, micron gauge, and vacuum pump and evacuate the lineset.
Once it is confirmed that the joints have a proper connection, pull a vacu-
um down to 500 microns.
After the vacuum is complete, close manifold gauge valve(s), and open
both the service valves fully, release the refrigerant into the system, and
start the system.
Move onto the next zone’s copper lines, connect them, and repeat steps
1-4.