Specifications
20 
Note:If no charging LED indication when the connection is normal 
Measure the PV input voltage at the PV terminals, input voltage must be greater 
than battery voltage before charging begins. 
5.3 Maintenance 
The following inspections and maintenance tasks are recommended at least two 
times per year for best controller performance. 
  Check that the controller is securely mounted in a clean and dry environment. 
  Check that the air flow and  ventilation  around the controller is not blocked. 
Clear all dirt or fragments on the heat sink. 
  Check all the naked wires to make sure insulation is not damaged for serious 
solarization,  frictional  wear, dryness,  insects  or rats etc.  Maintain or  replace 
the wires if necessary.   
  Tighten all the terminals. Inspect for loose, broken, or burnt wire connections. 
  Check and confirm that LED or Digital  Display indication is consistent with 
required.  Pay  attention  to  any  troubleshooting  or  error  indication  .Take 
necessary corrective action. 
  Confirm  that all the system  components are ground connected tightly  and 
correctly. 
  Confirm  that all  the  terminals  have  no  corrosion,  insulation  damaged,  high 
temperature or burnt/discolored sign, tighten terminal screws to the suggested 
torque. 
  Inspect for dirt, insects and corrosion, and clear up. 
Warning:Risk of electric shock! ! ! 
Make sure all the power is turned off before above operations, and then follow 
the corresponding inspections and operations.   