Installation Instruction

Table Of Contents
10
Choose one of the following built-in configurations.
Installation allowed only with non combustible back
wall
Option 1: A >= 12'' (305 mm) and B >= 28'' (711 mm)
Option 2: A >= 28'' (711 mm) and B >= 12'' (305 mm)
* Clearances from non-combustible materials are not
part of the ANSI Z21.1 scope and are not certified by
Intertek. Clearances of less than 3'' (76 mm) should be
approved by the local codes and/or by the local authority
having jurisdiction.
Island Installation (applicable both with non
combustible back wall and combustible back wall)
Option 1: A >= 12'' (305 mm) and B >= 28'' (711 mm)
Option 2: A >= 28'' (711 mm) and B >= 12'' (305 mm)
* purchased separately
** Clearances from non-combustible materials are not
part of the ANSI Z21.1 scope and are not certified by
Intertek. Clearances of less than 3'' (76 mm) should be
approved by the local codes and/or by the local authority
having jurisdiction.
Low Backguard Installation (applicable both with non
combustible back wall and combustible back wall)
Option 1: A >= 12'' (305 mm) and B >= 28'' (711 mm)
Option 2: A >= 28'' (711 mm) and B >= 12'' (305 mm)
* purchased separately
** Clearances from non-combustible materials are not
part of the ANSI Z21.1 scope and are not certified by
Intertek. Clearances of less than 3'' (76 mm) should be
approved by the local codes and/or by the local authority
having jurisdiction.
Technical Data
30” (5burners):
36” (6burners):

%
$
PLQ

%
$
Total connected load electric 1 A (120 W)
Total connected load gas
(natural gas)
48,000BTU/h
(14.1 kW)
Total connected load gas
(propane gas)
48,000BTU/h
(14.1 kW)
Total connected load electric 1 A (120 W)
Total connected load gas
(natural gas)
63,000BTU/h
(18.4 kW)
Total connected load gas
(propane gas)
63,000BTU/h
(18.4 kW)

%
$