This section is applicable for all the following port, application, and encryption blades supported on the
DCX 8510 chassis:
Blade DCX DCX-4S DCX 8510-4 DCX 8510-8
FC8-32E port blade No No Supported Supported
FC8-48E port blade No No Supported Supported
FC8-64 port blade Supported Supported Supported Supported
FC16-32 port blade No No Supported Supported
FC16-48 port blade No No Supported Supported
FC16-64 port blade No No Supported Supported
FCOE10-24 application
blade
Supported Supported No Supported (only on
slot 1)
NOTE
Cannot be in the same chassis with FC8-48E, FC8-64, FC16-48, FC16-64, FS8-18, or
FX8-24.
FS8-18 encryption blade Supported Supported Supported Supported
FX8-24 application blade Supported Supported Supported Supported
Time and items required
The replacement procedure for each blade takes less than 10 minutes. Removing and restoring
transceivers and cables may take longer depending on how many must be changed. The following
items are required for the blade and filler panel replacement:
Electrostatic discharge (ESD) grounding strap
Workstation computer
Replacement blade or filler panel
#2 Phillips screwdriver
Small form-factor pluggable (SFP+, mSFP, or QSFP) transceivers (as needed)
Optical and copper cables (as needed)
NOTE
For information about the transceivers that are qualified for the Brocade chassis, refer to Transceiver
removal and replacement on page 87.
Removing a blade
Complete the following steps to remove a blade.
Time and items required
Brocade DCX 8510-4 Backbone Hardware Reference Manual 65