Figure 4-16. Junction Box AC Power Cable Routing
2. Secure the cable between the AC power port and the AC power junction box. Leave sufficient slack in
the cable to allow it to be easily connected and disconnected from the AC power port.
3. Install any AC power supply wires that may be required between the AC junction box and the AC circuit
breaker box.
4. At the AC circuit breaker box, connect the AC power supply load wire to the circuit breaker.
5. Place the circuit breaker in the ON position and then test the connected end of the AC power cable for
proper voltage levels and correct polarity.
6. When testing is complete, PLACE THE CIRCUIT BREAKER IN THE OFF POSITION.
Danger: To avoid serious personal injury and equipment damage, always turn the AC power
off on the circuit breaker before connecting the any power cable to the AC power port.
7. Connect the power cable connector to the AC power port labeled “POWER”.
8. Tighten the coupling nut.
4.2.5.7 Slave Cable Connection
When two RU or more enclosures are installed for supporting multi-band. One is designated the Master
Remote Unit and each additional RU, up to two Units, are designated as slave Remote Units. The Master
and slave Unit(s) is specified by the frequency band. The Master Unit will separate the bi-directional signal
related to the frequency and provide the RF input signal to each slave Remote Unit. The connection
between Master and Slave is interfaced with the RF cable provided with the Remote Units.
Use the following procedure to install the antenna cable:
 All designated slave RUs arrive with two RF cables.
 Connect one RF cable to the port labeled “TX_OUT” on the MASTER Remote Unit User Interface.