G115WS/3 Installation Manual
Table Of Contents
- Contents
- 1 Safety Considerations and Symbol Descriptions
- 2 Product description
- 3 Moving the boiler
- 4 Installing the boiler
- 5 Installing the boiler
- 6 Commissioning the heating system
- 6.1 Bringing the system up to operating pressure
- 6.2 Checking the safety valve
- 6.3 Checking position of heat exchanger baffles
- 6.4 Preparing the heating system for operation
- 6.5 Starting up the control and the burner
- 6.6 Notes on commissioning the burner
- 6.7 Raising flue gas temperature
- 6.8 Manual reset high limit (STB)
- 6.9 Installing the burner door jacket
- 6.10 Commissioning log
- 7 Shutting down the heating system
- 8 Heating system servicing
- 9 Troubleshooting
- 10 Installation examples
- 11 Parts lists
- 12 Circuit diagrams
- Index
3
Moving the boiler
Logano G115 WS US/CA – 6 720 813 418 (2019/09) 13
3.2 Lifting and carrying the boiler
The boiler can be held and carried at the grip positions shown.
▶ Undo the transit screws.
Fig. 5 Lifting and carrying the boiler
3.3 Using transportation aids to transport the boiler
Moving the boiler with hand truck
▶ Place the hand truck (e.g. boiler trolley or sack truck) at the back of
the boiler.
▶ Secure boiler to hand truck using strapping.
▶ Move the boiler to the installation location.
Fig. 6 Moving the boiler with a boiler hand truck
The boiler is secured to the pallet by 2 screws for
transportation purposes.
CAUTION: Risk of injury from carrying heavy loads.
▶ Always lift and move the equipment with the
assistance of another person using the handle
positions shown.
7 747 019 141-05.1RS
CAUTION: Risk of injury if load is inadequately secured
during transportation.
▶ Use suitable means of transportation, e.g. the boiler
hand truck with strap.
▶ Secure the load against falling.
7 747 019 141-06.1RS