5.2 Fitting the water connections
5.2.1 Fitting the B-kit
The safety relief valve and the pressure/temperature gauge are mounted
on the supply manifold (included in B-Kit) on the VK boiler supply
connection as follows:
Fit and seal unmarked end of double nipple into connection VK on the
boiler.
Converter is paint-marked pink and stamped with the designation
NPT on the end with the 1¼ " NPT thread.
Seal 90° 1¼ " NPT street elbow on double nipple.
Fit and seal manifold to 90° elbow. The manifold can face in different
directions ( Fig. 14).
Seal pressure/temperature gauge to supply manifold.
Fig. 13 Checking thread length on double nipple
Fig. 14 Installing B-Kit
[1] 90° 1¼ " NPT street elbow
[2] Double nipple
[3] Supply manifold
[4] Pressure/temperature gauge
[5] Pressure relief valve
[6] 90° ¾ " NPT elbow
CAUTION: Risk of system damage from leaking
connections.
Support the pipes to the boiler to prevent them from
being under stress.
Do not fit the safety valve until the leak test ( Chapter
5.3, page 21) has been completed.
The relief valve must be installed in a vertical position.
We recommend installing a dirt filter (optional) in the
boiler return connection to reduce build-up of debris on
the water side.