Installation Manual
Table Of Contents
- Contents
- 1 Safety Considerations and Symbol Descriptions
- 2 Product description
- 3 Moving the boiler
- 4 Installing the boiler
- 5 Installing the boiler
- 6 Commissioning the heating system
- 6.1 Bringing the system up to operating pressure
- 6.2 Checking the safety valve
- 6.3 Checking position of heat exchanger baffles
- 6.4 Preparing the heating system for operation
- 6.5 Starting up the control and the burner
- 6.6 Notes on commissioning the burner
- 6.7 Raising flue gas temperature
- 6.8 Manual reset high limit (STB)
- 6.9 Installing the burner door jacket
- 6.10 Commissioning log
- 7 Shutting down the heating system
- 8 Heating system servicing
- 9 Troubleshooting
- 10 Installation examples
- 11 Parts lists
- 12 Circuit diagrams
- Index
12
Circuit diagrams
Logano G115 WS US/CA – 6 720 813 418 (2019/09) 57
Fig. 55 Circuit diagram 8
II
Z
Using Hydrolevel Hydrostat
1. Connect room thermostat or end switch to T and TV terminals on control.
2. Connect incoming 120VAC power source to the control.
3. Connect Line Voltage to terminal L1, and Neutral to terminal L2.
4. Connect the black wire from the Carlin 70200 to terminal B1 on control.
5. Connect the white wire from the Carlin 70200 to terminal B2 on control.
6. Connect the green wire from Carlin 70200 to ground screw on control.
7. Install a jumper between TT on Carlin 70200.
8. The pink wire from the Carlin “in-line heater” may be connected to the
red/white wire in the Carlin 70200 control.
6 720 813 418-04.1T
Carlin 70200 Series Primary Control
Field
installed
jumper
T
F
F
CAD
Cell Eye
Ground
T
BV
BV
A
A
L2
L1 IN
L1 OUT
LIMIT
MOTOR
VALVE
IGNITION