- 8.2.1 Installing B-Kit:
- 8.2.2 Installation of boiler drain (included in B-Kit)
- 8.2.3 Installation of system components
- 8.3 Filling heating system and checking for water leaks
- 8.4 Burner installation
- 8.5 Providing a fuel supply
- 8.6 Aquastat installation
- 8.7 Electrical connections
- 8.7.3 Electrical connections and connection of additional components
- WARNING!
- 8.7.4 Strain relief installation
- 8.8 Jacket panel installation
- 9 Placing the boiler in operation
- 9.9 Start-up protocol
- 11.3 Boiler cleaning
- 11.6 Inspection and maintenance protocols
- 16 Table of Key Words
14
Installation and maintenance instructions Logano G215 US oil/gas-fired boilers • Issue 11/2004
We reserve the right to make any changes due to technical modifications.
Placing the Boiler6
6 Placing the Boiler
This chapter details how to install and place the boiler in
the boiler room.
6.1 Clearances
Position the boiler at the recommended clearances
(Î Fig. 3). Reducing the minimum clearances makes
the boiler more difficult to access.
The boiler base or foundation must be perfectly flat and
level.
The burner door can be fitted with the hinge on the l.h.
or the r.h. side.
CAUTION!
SYSTEM DAMAGE
due to freezing temperatures.
z Install the boiler in a frost-free room.
Fig. 3 Boiler room clearances (see Tab. 11)
Mea-
sure
Distance
A Recommended 51 1/8"
minimum 39 3/8"
B Recommended 27 1/2"
minimum 15 3/4"
C Recommended 15 3/4"
minimum 3 7/8"
L
K
see "Technical Data" chapter
Tab. 11 Recommended and minimum clearances
(in inches)
NOTICE
Reduced clearances must comply with
local and state codes. The boilers are
designed for a side clearance of 6". Make
sure that there is a sufficient clearance
between combustible materials and the
chimney connection as specified by
NFPA 31 (distance of 18").
NOTICE
Where applicable, allow extra wall
clearances for additional components,
for example hot water tank, pipe
connections, flue gas muffler or other
components on the flue gas side.