Install Instructions
Table Of Contents
- 1 Safety Considerations
- 2 Product Description
- 3 Technical information
- 4 Packaging and Components
- 5 Moving the boiler
- 6 Placing the Boiler
- 7 Boiler block assembly
- 7.1 Assembly when delivered in sections
- 7.2 Check for leaks
- 8.2 Installation of water connections
- 8.2.1 Installing B-Kit:
- 8.2.2 Installation of boiler drain (included in B-Kit)
- 8.2.3 Installation of system components
- 8.3 Filling heating system and checking for water leaks
- 8.4 Burner installation
- 8.5 Providing a fuel supply
- 8.6 Aquastat installation
- 8.7 Electrical connections
- 8.7.3 Electrical connections and connection of additional components
- WARNING!
- 8.7.4 Strain relief installation
- 8.8 Jacket panel installation
- 9 Placing the boiler in operation
- 9.9 Start-up protocol
- 11.3 Boiler cleaning
- 11.6 Inspection and maintenance protocols
- 16 Table of Key Words
Boiler block assembly 7
15
We reserve the right to make any changes due to technical modifications.
Installation and maintenance instructions Logano G215 US oil/gas-fired boilers • Issue 11/2004
7 Boiler block assembly
The on-site installation is carried out using individual
sections if, because of physical limitations, a boiler block
cannot be assembled as a complete unit.
For installation of boiler supplied fully assembled
(Î Chapter 7.3, page 26).
Fig. 4 Boiler block in the assembled state
1 Foundation/installation location
2 Drain
3 Back section
4 Flue outlet
5 Connecting block
6 Central sections
7 Anchor rods
8 Front section
9 Burner door
1
3
4
6
7
8
5
9
2
7
CAUTION!
RISK OF INJURY
by not securing the boiler adequately
during transport.
z Use only suitable means for
transportation, e.g. a trolley with strap, a
stair or step trolley.
z Secure the load against falling.