Install Instructions
Table Of Contents
- 1 Safety Considerations
- 2 Product Description
- 3 Technical information
- 4 Packaging and Components
- 5 Moving the boiler
- 6 Placing the Boiler
- 7 Boiler block assembly
- 7.1 Assembly when delivered in sections
- 7.2 Check for leaks
- 8.2 Installation of water connections
- 8.2.1 Installing B-Kit:
- 8.2.2 Installation of boiler drain (included in B-Kit)
- 8.2.3 Installation of system components
- 8.3 Filling heating system and checking for water leaks
- 8.4 Burner installation
- 8.5 Providing a fuel supply
- 8.6 Aquastat installation
- 8.7 Electrical connections
- 8.7.3 Electrical connections and connection of additional components
- WARNING!
- 8.7.4 Strain relief installation
- 8.8 Jacket panel installation
- 9 Placing the boiler in operation
- 9.9 Start-up protocol
- 11.3 Boiler cleaning
- 11.6 Inspection and maintenance protocols
- 16 Table of Key Words
Boiler block assembly 7
17
We reserve the right to make any changes due to technical modifications.
Installation and maintenance instructions Logano G215 US oil/gas-fired boilers • Issue 11/2004
7.1.2 Preparing push nipples and nipple ports
z Clean the nipples with a cloth soaked in cleaning
agent.
z Evenly coat the nipples with red lead putty.
z Place nipple straight in the top and bottom boiler hub
of the back section and hammer in a crosswise
pattern.
z Remove any burrs with a file.
7.1.3 Preparing the intermediate section
Prepare the central section in the same way as the back
section (Î Chapter 7.1.1, page 16).
Fig. 7 Driving nipples home
1 Nipple in the upper boiler hub
2 Nipple in bottom boiler hub
30
2
1
1 1/8
NOTICE
After driving in the nipple leave it projecting
approx. 1 1/8" from the boiler hub.
Fig. 8 Preparing the central section
1 Boiler hub sealing face
2 Packing grooves
1
1
2