Install Instructions
Table Of Contents
- 1 Safety Considerations
- 2 Product Description
- 3 Technical information
- 4 Packaging and Components
- 5 Moving the boiler
- 6 Placing the Boiler
- 7 Boiler block assembly
- 7.1 Assembly when delivered in sections
- 7.2 Check for leaks
- 8.2 Installation of water connections
- 8.2.1 Installing B-Kit:
- 8.2.2 Installation of boiler drain (included in B-Kit)
- 8.2.3 Installation of system components
- 8.3 Filling heating system and checking for water leaks
- 8.4 Burner installation
- 8.5 Providing a fuel supply
- 8.6 Aquastat installation
- 8.7 Electrical connections
- 8.7.3 Electrical connections and connection of additional components
- WARNING!
- 8.7.4 Strain relief installation
- 8.8 Jacket panel installation
- 9 Placing the boiler in operation
- 9.9 Start-up protocol
- 11.3 Boiler cleaning
- 11.6 Inspection and maintenance protocols
- 16 Table of Key Words
28
Installation and maintenance instructions Logano G215 US oil/gas-fired boilers • Issue 11/2004
We reserve the right to make any changes due to technical modifications.
Boiler block assembly7
z Secure both slotted hinge lobes with one M12 × 25
hexagon bolt each to the burner door.
z Hook the burner door with the hinge lobes onto the
hinge pins.
z Close the boiler door.
7.4.4 Fitting the boiler jacket
Installation of the boiler back panel
z Screw spacer pins to the rear section.
Fig. 32 Hooking on the burner door (here: on the r.h. side)
1 M12 × 25 hexagon bolt
CAUTION!
SYSTEM DAMAGE
due to leaking burner door.
z Tighten the hexagon bolts of the burner
door evenly.
Fig. 33 Spacer pin installation