Install Instructions

16 103448-08- 9/16
III. Pre-Installation and Boiler Mounting H. Boiler Stacking (continued)
Figure 3: Stacking Boiler Attachment
Bracket Placement
boiler ue gas condensate line construction and
condensate disposal. Terminating individual
boiler condensate lines into common pipe prior
to drain disposal is permissible, providing
common pipe has sufcient ow capacity
to handle combined condensate volume of
stackable combination.
b. Gas Piping - Follow instructions in Section
VII “Gas Piping” of the manual for sizing
and installation of an individual boiler. When
common gas piping is sized, insure it will have
adequate capacity for combined input (CFH
gas ow) of the selected stackable boiler
combination.
c. Water Piping and Trim - Follow instructions
in Section VI “Water Piping and Trim” of the
manual for system piping and boiler secondary
piping selection/sizing based on combined
heating capacity and/or gross output of
the selected stackable boiler combination.
Follow instructions of Section VI “Water
Piping and Trim” for each individual boiler trim
installation.
d. Electrical - Follow instructions in Section VIII
“Electrical” of the manual to wire individual
boilers.
WARNING
Asphyxiation Hazard. No common manifold
venting is permitted. Each boiler must have its
own individual vent and combustion air pipes
and terminals.
For side-wall venting individual model vent
terminals must terminate not closer than 12
inches horizontally and three (3) feet vertically
from each other in order to prevent combustion
air contamination. For vertical through the roof
venting, individual vertical vent terminals, if
level with each other, must be spaced no closer
than 12 inches horizontally. If vertical terminals
cannot end in one plane, they must be spaced no
closer than three (3) feet horizontally.
If vertical vent terminals cannot end in one
plane, they must be spaced no closer then three
(3) feet horizontally.
Follow instructions in Section IV “Venting”
of the manual for specics of individual boiler
vent termination. Follow instructions in Section
V “Condensate Disposal” for each individual