VIII. Service Instructions (continued)
A.  General 
  Inspection and service should be conducted annually. 
Turn off electrical power and gas supply while 
conducting service or maintenance. Follow instructions 
TO TURN OFF GAS TO APPLIANCE. See Figure 21.
CAUTION
Label all wires prior to disconnection when 
servicing controls. Wiring errors can cause 
improper and dangerous operation. Verify proper 
operation after servicing.
B.  Low water cutoff
  Clean probe.
1.  Drain boiler to point below Tapping "L".
2.  Disconnect the (3) wire multi pin connector from the 
control and disconnect the control's black wire from 
the probe's screw terminal. 
3.  Remove control from probe.
4.  Unscrew probe from Tapping "L".
NOTICE
Carefully remove, clean, and reinstall probe.  
Platinum guard ring must not be exposed to 
rough treatment, or useful life of probe may be 
shortened.
5.  Remove deposits from probe using diluted 
phosphoric acid (H
2
PO
4
) solution, 3 parts water to 1 
part phosphoric acid. Normal operation will occur 
with up to 0.2 inch of contamination. If scale or 
contamination exceeds 0.2 inches clean probe more 
frequently.
6.  Reinstall probe in Tapping "L". Mount control on 
probe. Attach control's black wire to probe's screw 
terminal and reconnect the (3) wire multi pin 
connector to the control.
C.  Water Feeder and Additional Low Water Cut-Off
  Refer to manufacturer's instructions.
D.  Vent System  Inspect for obstructions, soot 
accumulation, proper support, and deterioration of pipe, 
ttings,andjoints.
1.  Clean vent terminal screens. Vent terminal must be 
free of obstruction, undamaged, with screens 
securely in place.
2.  Vent terminal and wall thimble (if used) must be 
weather-tight.
3.  Vent pipe must be full round shape, and show no 
damage from impact or excessive temperature.
4.  Vent pipe must be supported at minimum 5 foot 
intervals and must not sag.
5.  All joints must be secure and watertight.
6.  Condensate drain must have minimum 6 inch trap 
andallowcondensatetoowfreely.Toclean:
a. Disconnectcondensatedrainfromdraintting.
b.  Flush condensate drain with water. Fill trap with 
water.
c. Securelyfastencondensatedraintodraintting,
providing gas-tight and watertight seal.
7.  If vent pipe must be disassembled for removal of 
obstructions or resealing of joint, see Venting 
Section.
E.  Boiler Flue Passages. Inspect for blockage or soot 
accumulation.
1.  Remove Main Burners.
a.  Disconnect Pilot Tubing from Gas Valve.
b.  Disconnect Igniter/Sensor Wire and Pilot Ground 
Wire from Ignition Module.
c.  Disconnect (2) wires to Flame Roll-out Switch.
d.  Remove Burner Access Panel.
e.  Mark manifold with location of Main Burner 
with Pilot Bracket.
f.  Hold Main Burner on throat. Lift slightly to clear 
orice.PullMainBurnerfromcombustion
chamber. Main Burner with Pilot Bracket can 
only be removed by lifting at 45° angle after 
adjacent Main Burner to right is removed.
2.  Disconnect Junction Box to Vestibule Wiring 
Harness from Blower.
3.  Remove (4) locknuts securing vent connector. See 
Figure 7. Disconnect vent connector and vent pipe 
from blower outlet. 
4.  Remove Jacket Top Panels.
5.  Disconnect Silicone Tubing from Canopy. Pull 
tubing through Blower Access Panel into vestibule.
6.  Remove Blower Access Panel.
7.  Loosen (4) carriage bolts. Remove Canopy/Blower 
Assembly.
8. RemoveGasketandFlueGasBafes.InspectFlue
Bafesfordeterioration.
9. Inspectuepassages.Cleanwithuebrush.See
Figure 22.
10.  Inspect heating surface in combustion chamber. 
Clean with straight handle wire brush.
12. InstallFlueGasBafes.
13.  Install new Gasket (Key No. 2E). Do not reuse 
existing material.