Installation Guide

Questions? (888) 788-2254
www.CaliBrands.com
Odyssey Flooring Installation Guide
Before you begin installation, remember to P.A.C.E. yourself with the checklist below. Full installation
instructions and maintenance guidelines can also be found online at www.CaliBrands.com
Pre-Installation
P ACE
EXPANSION
GAPS
Engineered ooring can be used in areas ranging from
30% to 55% relative humidity.
Leave at least 1/2” expansion spaces between ooring and ALL
vertical objects (walls, cabinets, pipes, etc.) Large ooring runs
may require additional expansion space. For oating oors, use
transition moldings between rooms and doorways 3ft. or less.
Undercut door jambs and casings to provide adequate
expansion space. Do not screw or nail cabinetry or other
permanent xtures to a oating oor.
30-55% rH
1/2” Expansion Gap
1/2” Spacer
Baseboard
PA C E
CONTROL
ENVIRONMENT
Make sure the suboor is at, level, clean and free of debris.
New concrete must be cured for at least 60 days. Test the
suboor moisture prior to installation and apply an
appropriate moisture barrier. CALI recommends Titebond®
531+ on concrete suboors. Although, other moisture
barriers are available.
MOISTURE
BARRIER
Use a Moisture Barrier on Concrete
PA CE
ACCLIMATE
FLOORING
For Engineered ooring, lay boxes on the oor and only open
box ends as shown above.
Acclimate your oor as close to
the installation area as possible, for 72 hours in normal
living conditions.
Acclimate Your Engineered Flooring For 72 Hours
PACE
PREPARE
THE SUBFLOOR