WATERPROOF MEMBRANE/ SHOWER PAN LINER
INSTALLATION
(see figure 3)
Waterproof membrane/Shower pan liner shall be
installed per manufacturer instructions and local building
& plumbing codes.
1. Waterproof membrane/shower pan LINER [4]
material should be between drain BODY [1] and
COLLAR [5].
2. Place COLLAR [5] over BOLTS [6] in up or down
position (based on flooring material thickness and/or
local building & plumbing codes) and rotate to lock
COLLAR [5] in place. Note: COLLAR [5] may be
installed in up position for an additional 7/8” in
height.
3. Tighten all four BOLTS [6] snug.
4. Test waterproof membrane/pan liner installation in
accordance with local building & plumbing codes.
Note: WEEP [7] holes shall be clear of any residual pan
liner material.
THROAT/GRID HEIGHT ADJUSTMENT
(see figure 4)
1. To obtain proper grid height, rotate THROAT [8] to
raise or lower. One (1) complete rotation of
THROAT [8] is equal to 1/8” in vertical adjustment.
2. Proper height should be determined by flooring
contractor.
3. Before the final mortar application it is suggested to
place some pea GRAVEL [9] over WEEP [7] holes
to prevent blockage of the holes.