User's Guide

Table Of Contents
6 Installation
50
6 Installation
This section provides instructions for installing a PTP 500 link.
It is advised that the link be configured and tested on a bench before the final installation of
the units on site. Providing it is safe to do so, the installer should take the bench testing
process to the point where a radio link is established. For more information, see the
Deployment Guide.
CAUTION
Motorola recommends that only qualified personnel undertake the installation of a
PTP 500 Series Bridge solution.
We recommend that the practices and procedures detailed in the Motorola manual
R56 "STANDARDS AND GUIDELINES FOR COMMUNICATION SITES"
(68P81089E50) be applied to all new site build activities. This manual is provided on
the PTP 500 CD-ROM.
The standard PTP 500 Series installation procedure consists of the following stages:
1. Prepare for installation as described in Section 6.3 “Preparation”.
2.
Mount the ODUs as described in Section 6.4 “Mounting the ODU
s”.
3. Connect the equipment as described in Section 6.5 “Connecting Up”.
4.
Establish a radio link as described in Section 6.6 “Establishing a Radio Link”.
Dep
ending upon the options required, see also the following sections:
1. If a connectorized PTP 500 variant is to be installed, see Section 10 “Connectorized
PTP 500 Seri
es Bridge”.
2. If an E1/T1 link is to be installed, see Section 11 “E1/T1 Installation Guide”.
3.
If the link is to be encrypted, see Section 13 “AES Encryption”.