Start-Up Checklist
Installation
Make sure the unit is secured to the floor or mounting surface. The
ladder(s) and platform(s) must be tightened and set up according to
OSHA requirements. Ducting and piping must be secured and routed out
of the way of traffic whenever possible to avoid injury. Ducting must also
be free of all debris including moisture.
Interior of Dirty Air Plenum
In a bottom bag removal collector, inspect the filter bag assemblies
referring to the “Bag and Cage Installation” section of this manual.
Improperly installed bags may allow dusty air to enter the clean air
plenum.
High-level indicator, if so equipped, should be connected below the
material inlet(s) to avoid over filling the hopper.
Interior of Clean Air Plenum
The blowholes in the blowpipes must be centered over the filter bags.
On top bag removal collectors verify that bags and cages are properly
installed.
On top bag removal collectors the bulkhead fittings must be checked for
proper tightness and that the blowpipes are secured at both ends.
Exterior of Dust Collector
Access doors, inspection ports and spring-loaded relief vents should seat
effectively to prevent leakage.
All bolts must be properly tightened.
Operate any equipment connected to the dust discharge of the dust
collector. Check the rotation of any motor driven equipment such as
rotary airlocks, horizontal unloading valves, live bottom bin activators and
screw conveyors. Check slide gates and butterfly valves for binding.