Canon model VB-H610D A&E Specifications
OWNER / May 16, 2013 28 23 00 - 17 Video Surveillance System
e. Where conduit penetrates fire-rated walls and floors, seal opening with UL listed
fire rated sealer or other methods as approved by codes.
f. No exposed conduit, raceway, or junction box shall be installed within any office
area.
g. Install all boxes straight and plumb.
h. Do not support conduit from mechanical, plumbing, or fire sprinkler systems.
i. Drill or core drill all holes in walls, ceilings, or floors where required for new
conduits. Do not cause damage to any structural steel or other structural support
member by drilling or cutting.
j. Do not use flexible conduit in lengths longer than six (6) feet.
1. Outdoor Requirements:
a. Where conduit penetrates exterior walls, seal opening around conduit in an approved
manner to make watertight.
b. Use galvanized straps and fasteners on all exterior conduit.
c. All exterior boxes will only be used to aid in pulling the cable between points.
G. Penetrations
Do not penetrate any roof, flashing, exterior wall, or parapet without prior approval from
OWNER’s designated Construction Project representative.
I. Grounding
Provide earth grounding of equipment as required by equipment manufacturer. Earth ground
shall be connected to ground rod or approved cold water pipe. Electrical or telephone ground
connections shall not be used as earth grounds. Connections to mounting posts or building
structural steel shall not be used as earth grounds.
J. Power To Security Equipment
1. Power all equipment from 120 VAC circuit dedicated for security use, except as noted.
Mark all panel circuit breakers with labels worded “Security Equipment - Do Not
Operate”, or equivalent.
2. All plug-in transformers shall be located at the security control panels. Secure all low-
voltage plug-in transformers to outlet with screw or strap. Clearly label all transformers to
identify purpose and use.
K. Cutting And Patching
The Contractor shall be responsible for all cutting, fitting or patching that may be required to
complete the Work.
L. Painting
All conduit, fittings, and junction boxes shall be painted to match the existing surfaces they are
mounted on. This work may be performed after the system is fully operational.
3.03 FIELD QUALITY CONTROL
A. Final Tests & Inspection
The Contractor shall coordinate with the OWNER’s Project Manager for final tests and
inspections in the presence of the Project Manager, System Designer/Consultant, and a factory
support person from the manufacturer.
B. Training