Canon model VB-S900F A&E Specifications
OWNER / November 22, 2013 28 23 00 - 17 Video Surveillance System
1. Power all equipment from 120 VAC circuit dedicated for security use, except as noted.
Mark all panel circuit breakers with labels worded “Security Equipment - Do Not
Operate”, or equivalent.
2. All plug-in transformers shall be located at the security control panels. Secure all low-
voltage plug-in transformers to outlet with screw or strap. Clearly label all transformers to
identify purpose and use.
K. Cutting And Patching
The Contractor shall be responsible for all cutting, fitting or patching that may be required to
complete the Work.
L. Painting
All conduit, fittings, and junction boxes shall be painted to match the existing surfaces they are
mounted on. This work may be performed after the system is fully operational.
3.03 FIELD QUALITY CONTROL
A. Final Tests & Inspection
The Contractor shall coordinate with the OWNER’s Project Manager for final tests and
inspections in the presence of the Project Manager, System Designer/Consultant, and a factory
support person from the manufacturer.
B. Training
1. The training of all personnel shall be performed on-site by the Contractor and a factory
trainer provided by the manufacturers.
2. The manufacturer shall provide a training tutorial and all handout material.
3. The manufacturer shall also supply video recording of either the actual on-site training or
a copy of in-house training at the manufacturer’s office.
END OF SECTION