Specifications

31
FIELD POWER SUPPLY (CONT.)
30GX 080-160
Electrical box
FIELD CONTROL WIRING
Refer to the Certified Electrical Wiring Diagram supplied with
the unit for the field control wiring of the following features :
- Cooler pump interlock (mandatory)
- Remote on/off switch
- Remote Heat / Cool switch
- Demand limit external switch 1
- Demand limit external switch 2
- Remote dual set point
- General alarm contact
- Cooler pump control (Option)
- Outdoor air temperature (Option)
- Remote Reset 4-20 mA (Option)
- Demand limit 4-20 mA (Option)
PE M10
GROUND FIELD
CONNECTION
Ø 12
Power terminal block Main disconnect switch
S mm
2
30GX B (mm) Min. Max.
080 540 120 300
090-105 540 150 300
115 540 185 300
125-135 540 240 300
150-160 540 2x95 2x120
S mm
2
30GX A (mm) B (mm) Min. Max.
080 46 510 120 300
090-105 46 510 150 300
115 46 510 185 300
125-135 46 510 240 300
150 46 510 2x95 2x185
160 62 510 2x95 2x185
IMPORTANT
Before the connection of the main power cables (L1 - L2 - L3) on the power terminal block, it is imperative to check the right order
of the 3 phases before proceeding to the connection on the terminal block or the main disconnect switch.
PE M12
GROUND FIELD
CONNECTION