–25–
In case of wireless remote control (Forced
test operation is performed in a different
way.)
REQUIREMENT
For the operation procedure, be sure to follow
the Owner’s Manual.
Finish the forced cooling operation in a short
time because it applies excessive strength to
the air conditioner.
A test operation of forced heating is
unavailable. Perform a test operation by heating
operation using the switches of the remote
control.
However heating operation may be not carried
out according to the temperature conditions.
Check wiring/piping of indoor and
outdoor units
1. When is pushed button for 10 seconds
or more, “Pi!” sound is heard and the
operation changes to a forced cooling
operation. After approx. 3 minutes, a
cooling operation starts forcedly.
Check cool air starts blowing. If the
operation does not start, check wiring
again.
2. To stop a test operation, push button
once again (Approx. 1 second).
The louver closes and the operation stops.
Check transmission of remote control
1. Push “START/STOP” button of the remote
control to check an operation can also start
by the remote control.
“Cooling” operation by the remote control
may be unavailable according to the
temperature conditions.
Check wiring/piping of the indoor and
outdoor units in forced cooling operation.