Product specifications

Device Management FOUNDATION Fieldbus
272 3BDS011222-510 B
It is possible to switch directly between configuration and commissioning modes.
The following steps give you instructions how to configure and commission an FF
Application using Fieldbus Builder FF:
Step 1: Check, Save, and Upload FF Libraries
Step 2: Create and Configure an HSE Subnet
Step 2a: Create HSE Subnet
Step 2b: Configure HSE Subnet
Step 3: Configure the FF Application
Step 4: Load the FF Application
Step 4a: Precommissioning
Step 4b: Commissioning
Step 5: Using FF Data
Prerequisites and Requirements
The following requirements must be met, in order to be able to carry out the steps
described here.
An 800xA system has been created and started.
The following system extensions have been added:
AC 800M/C Connect,
Fieldbus Builder FF,
FF Device Integration Library - Basics.
Device object types for those field devices intended to be used in the project
have been added to the FF device library. Refer to Device Library Wizard on
page 217.
The Plant Explorer of Engineering Workplace or Plant Explorer Workplace has
been started.
The user has Configure and Download permissions.