Product specifications

Control Structure Section 2 Configuration
34 3BDS011222-510 B
To configure the task“s properties:
1. Right-click on the task object.
2. Click Task Properties.
3. In the Task Properties dialog edit the required properties and click Apply.
4. Click OK.
Connect Application to Task
To connect an application to a controller and a task:
1. In Plant Explorer switch to the Control Structure.
2. Right click the Applications object below the corresponding controller object.
3. Click Insert Object....
4. In the Insert Object dialog browse to the existing application child object of the
Applications object below the project object and select it.
5. Press Insert.
6. Press Close to leave the dialog.
7. Right click the inserted application object.
8. Click Project Explorer.
9. In the Control Builder M Professional project window right click the already
selected application.
10. Click Task Connection.
11. From the offered list of tasks select an appropriate task.
12. Press OK.