Installation Instructions

Installation Instructions
Cedar Impressions
®
D9" Staggered
Rough-Split Shakes and Mitered Cornerpost
These instructions describe and illustrate the steps
involved in installing CertainTeed siding and trim. Their
purpose is to provide detailed information and how-to
tips that will simplify the installation process. CertainTeed
shall not accept any liability or responsibility under its
written warranty for failure caused by application that
does not meet our minimum requirements for proper
installation. These requirements are outlined throughout
the
CertainTeed Installation Guide (CTS205). Any
deviations from these requirements should be approved
in writing by CertainTeed Corporation.
Important
This product is not designed for roof application. It is
designed solely for installation on vertical surfaces.
Panels must be installed with nails over a solid substrate
with nail holding strength such as plywood, oriented
strand board, or existing wood siding (minimum 7/16"
thick). This product cannot be installed with staples.
NOTE: Each panel must be nailed through the round hole
in the center of the nail hem to control the direction of
normal expansion and contraction. If you are installing a
partial panel and the center nail hole has been cut off, drill
a nail hole in the center of the nail hem of the cut panel
and nail through it.
Panel Spacing at Different Temperatures
As with any plastic siding, Cedar Impressions
®
expands
and contracts with changes in temperature. For this
reason, it is important that you space the panels accor
ding
to the panel temperature at the time of installation. Failure
to provide the proper spacing according to these
temperature ranges may result in gaps that are too large or
too small, thereby creating the potential for side lock tabs
disengaging, panel distortion, or buckling. Spacing of
panels previously installed at a different temperature does
not r
equire adjustment.
Each panel has a
PanelThermometer
that displays
panel temperature and indicator lines
that serve as
guides for pr
oper spacing between the panels. The
PanelThermometer is located on the upper right-hand
corner of the panel; the indicator lines are on the upper
left-hand cor
ner (figur
e 1).
Note that the panel
temperature may
change throughout
the day. Space the
panels according
to the panel
temperature at the
time of installation.
The cells on the PanelThermometer will change color to
indicate the temperature of the panel.
NOTE: If two temperature cells on the PanelThermometer
show a color change, use the brighter color as the indicator.
PanelThermometer Temperature
Reading Indicator Lines
0 Set to 0 line
30 Set to 30 line
65 Set to 65 line
100 Set to 100 line
130 Set to 130 line
160 Butt panels tight
If the brighter cell is between the numbered temperature
cells, position the panel between the corresponding
temperature indicator lines.
Example: If the
PanelThermometer reads 65, align the second panel to
the 65 temperature indicator line on the first panel. If the
cell between the 65 and 100 is brighter, position the panel
between the 65 and 100 temperature indicator lines.
First course
Strike a level line around the house and install Cedar
Impressions Starter. If you plan to use Cedar Impressions
Mitered Cornerpost, make sur
e the
starter strip is installed to the edge of the
corner. An alternative method of starting
Cedar Impressions is to use
J-channel in place of starter strip to
receive the bottom edge of the panel.
1) Cut 2" off the top course of the panel
at indicator “A,” which is located
above the nail slots (figure 2).
2) Starting on the right side
of the wall, hook the
bottom locking leg of the
panel into the starter strip
and slide panel
into the cornerpost or
r
eceiving channel
(figur
e 3). Leave 1/4"
space between the panel
and the cor
ner for expansion. If you ar
e planning to
install the Miter
ed Cor
nerpost, space the panel 3"
from the corner.
3) Fasten the panel to the wall by
first nailing through
the round center
hole in the nailing
hem at the top of
the panel. Continue
nailing the panel
with 5 nails: one in the right-end nail slot
and one at each of the QuickRefer
ence™ Nail Mark
Indicators (figur
e 4). Leave 1/8" to 1/16" between the
nail heads and the panel to allow fr
eedom of
movement during normal expansion and contraction.
1/4"
2"
“A”
panel temperature indicator lines
QuickReference
Nail Mark Indicators
FIGURE 4
FIGURE 3
FIGURE 2
FIGURE 1
D9" Staggered Rough-Split Shakes and Mitered Cornerpost Installation Instructions | 1 of 3

Summary of content (3 pages)