Step 1
Measure for placement of Green Glue Noiseproong Clips using layout guidelines listed above.
Mark locations and install clips using appropriate screws.
Recommended screws by stud type
Wood: Use #8 x 2-1/2”
coarse thread screws
Steel: Use #8, 10 or 12 x 1-5/8”
Type S self-tapping screws
Concrete: Use 3/16” dia x 2-1/4”
Tapcon or equal anchor Screw
Outermost clips must be spaced at every interval
10’
(2)
24”
(1)
48”
16”
(4)
6”
(3)
3”
Layout pattern for Green Glue Noiseproong Clips
Install ceiling drywall before walls to allow for a
re stop by butting ceiling drywall to studs
Green Glue Noiseproong Clip layout
(1) Clips are spaced no further than
48 inches apart horizontally
(2) Hat channel must not be spaced
more than 24 inches vertically
(3) Bottom clips must be less than 3
inches from the oor
(4) Top clips must be less than 6
inches from the ceiling
*Clips must be placed at the outermost
studs on every piece of hat channel
Product Specications
Width 1.25 inch
Height 4.25 inch
Depth 1 inch
Weight .025 lbs
Max Spacing 48” on center
Recommended Load 36 lbs ~ 3 drywall layers
Max Safe Load 46 lbs ~ 4 drywall layers
Fail Load 300 lbs ~ 27 drywall layers